Recreation and Wellness Center:
Projected Start Date ( Phase I ): Summer 2006
Projected Completion Date ( Phase I ): Summer 2007
Projected Completion Date ( Phase II ): Fall 2007
Projected Completion Date ( Phase III ): Winter 2007
Size:124,710 New Square Feet
14,505 Renovated Square Feet
University Center Expansion, Phase III:
Projected Start Date: January 2007
Projected Completion Date: June 2008
Size: 59,078 New Square Feet
68,285 Renovated Square Feet
Laurel Village (Student Housing Expansion), Phase II:
Projected Start Date: December 2006
Projected Completion Date ( Phase I ): June 2007
Projected Completion Date ( Phase II ): May 2008
Size: 185,000 Square Feet
Thermal Energy Plant & Garage:
Start Date for Thermal Energy Plant: August 2006
Completion Date for Thermal: February 2008
Start Date for Garage: November 2006
Completion Date for Garage: February 2008
Size: 17,755 Square Feet - Thermal Plant,
179,933 Square Feet - Garage
Roadrunner Cafe Expansion:
Projected Start Date: April 2007
Projected Completion Date: May 2008
Size:7,000 Square Feet